Bond 2025 Updates
- New Tomball Intermediate
- Multi-Program Activity Centers
- Transportation Center
- Original Tomball High School Stadium
- New Buses & White Fleet
- Elementary Campus Refresh
- Student & Staff Device Refresh
- Safety & Security
- Facility Infrastructure
- Athletics
New Tomball Intermediate
October 2026
-
During the September 2026 Board meeting, the Tomball ISD Board of Trustees awarded the construction of the new Tomball Intermediate School to ICI Construction.
-
The new campus is scheduled to open in August 2028.

May 2026
- Huckabee has completed the design development phase and moved into the construction documents phase of the project.
- During the construction documents phase, all architectural, structural, civil, mechanical, electrical, plumbing, and life‑safety components are finalized and developed into detailed drawings and written specifications that will be used to price, permit, and construct the facility.

April 2026
- Huckabee has completed the schematic design phase of the Tomball Intermediate School project, and moved into design development.
- This phase will refine the conceptual design into detailed plans that integrate structural, mechanical, electrical, and plumbing systems as well as final material selections.
March 2026
- Huckabee has completed the schematic design phase of the Tomball Intermediate School project, and presented initial renderings to the TISD Board of Trustees during the February 2026 workshop meeting.



February 2026
- Huckabee Architect’s schematic design phase has reached 98% completion and will present initial renderings at the February Board meeting.
January 2026
-
Tomball ISD held multiple meetings with Huckabee Architects during December with a focus on the design and layout of the new Tomball Intermediate Campus.
-
Additional meetings will be held throughout January as we work to finalize the design phase of this project.
December 2025
- Tomball ISD held multiple meetings with Huckabee Architects during November with a focus on the design and layout of the new Tomball Intermediate Campus.
- Additional meetings will be held throughout December and January as we work to finalize the design phase of this project.
November 2025
- Huckabee Architects has completed the programming portion of the design phase and held the first schematic design meeting on October 31, 2025.
- Geotechnical work is expected to begin in November, following final building placement on the site.
October 2025
- Huckabee Architects was selected by the Board of Trustees in June 2025 to serve as architects for the new Tomball Intermediate campus.
- Tomball ISD is currently working with Huckabee to complete the design phase of the project, with District leadership participating in frequent programming and planning meetings over the last three months.

Multi-Program Activity Centers
June 2026
- During the June 2026 Board meeting, PBK Architects presented the schematic design of the Multi-Program Activity Centers (MPACs). The plans align with the exact size and dimensions shared with voters during the 2025 Bond Election, ensuring the project is being delivered as presented to the community.
- The 80-yard field design was intentionally developed to accommodate site constraints across all three comprehensive high school campuses while ensuring equitable facilities and opportunities for students districtwide. An MPAC will be constructed at each comprehensive high school, featuring an 80-yard turf field plus a 10-yard end zone.
- MPACs will also include a drop-down netting to accommodate multiple student groups, ample storage, two golf simulators, and a fully air-conditioned space.
Multi-Program Activity Center Schematic Design



May 2026
- PBK has completed the schematic design phase of the Multi-Program Activity Centers project, and moved into design development.
- This phase will refine the conceptual design into detailed plans that integrate structural, mechanical, electrical, and plumbing systems as well as final material selections.
January 2026
- Tomball ISD continues to hold planning meetings with PBK Architects as we work through the design process for the Multi-Program Activity Centers.
December 2025
- Tomball ISD continues to hold planning meetings with PBK Architects as we work through the design process for the Multi-Program Activity Centers.
November 2025
-
In October 2025, the Tomball ISD Board of Trustees approved the selection of PBK Architects to provide architectural services on the Multi-Program Activity Centers that will be built at each high school campus.
-
The official kickoff meeting to begin the design phase will be held on November 12, 2025.
Transportation Center
October 2026
-
Site development for the Transportation Center parking lot expansion continues to progress as expected.
-
Tree and vegetation removal has been completed to allow site work to commence on the underground infrastructure.

September 2026
- Site development for the Transportation Center parking lot expansion has continued through August with the clearing of trees and undergrowth nearing completion.
-
The expansion project will increase parking space to accommodate a total of 365 buses and 304 staff vehicles.
-
Also included in the scope of work will be the realignment of the main entrances, new security gate, updated lighting, security fencing and security cameras.
August 2026
- Gamma Construction began site development work on the parking lot expansion in July.
- The expansion project will increase parking space to accommodate a total of 365 buses and 304 staff vehicles.
- Also included in the scope of work will be the realignment of the main entrances, new security gate, updated lighting, security fencing and security cameras.
June 2026
- At the June 2026 Board meeting, the Board of Trustees approved the selection of Gamma Construction to complete the expansion of the Transportation parking lot.
- The expansion project will increase parking space to accommodate a total of 365 buses and 304 staff vehicles.
- Also included in the scope of work will be the realignment of the main entrances, new security gate, updated lighting, security fencing and security cameras.
February 2026
-
The design phase of the parking lot expansion is underway with survey and geotechnical studies being conducted in January 2026.
November 2025
-
Phase 1 of the Transportation Center expansion project will focus on additional parking space for both buses and Transportation staff.
-
A kickoff meeting was held on October 15, 2025 to begin the initial design phase of the project.
Original Tomball High School Stadium
September 2026
- During Summer 2026, Hellas Construction completed the replacement of Tomball High School’s artificial turf football field and track surface.
- Enhancements were made to include Tomball High School branding on the turf and colored exchange zones for the track surface.
August 2026
- The artificial turf and track replacement at Tomball High School began in June 2026 and is nearing final completion with the field available for use this August.

June 2026
- Work has begun at Tomball High School to replace the existing artificial turf and track surfaces.
- The project is scheduled to be completed this summer and ready for use this August.

May 2026
- During the April 2026 Board meeting, the Board of Trustees approved the purchase and replacement of the field turf and track surface at Tomball High School.
- The turf and track are scheduled to be replaced during Summer 2026 and will be ready for use this August, a full year ahead of our original schedule.
New Buses & White Fleet
September 2026
-
In November 2025, the Tomball ISD Board of Trustees approved the purchase of 40 additional school buses.
-
Delivery of those buses was expected to take almost a year to complete. However, the Tomball ISD Transportation department was able to work with our vendor to get those buses delivered over the summer and on the road to start the 2026-2027 school year.
May 2026
- In August 2025, the Tomball ISD Board of Trustees approved the purchase of 52 new school buses and white fleet vehicles.
- As of April 2026, all buses and white fleet vehicles have been received and placed into service.


January 2026
- In December 2025, the Tomball ISD Board of Trustees approved the purchase of 40 new school buses that will be delivered in 10-12 months.
- This purchase follows an initial order of 24 buses in August 2025 that are expected to be delivered by January-February 2026.
October 2025
- In August 2025, the Tomball ISD Board of Trustees approved the purchase of the 52 new school buses and white fleet vehicles detailed below:
- 7 buses for replacement
- 17 buses for growth
- 17 white fleet vehicles for the Maintenance Department
- 11 white fleet vehicles for the Custodial Department
- White fleet vehicles are already being delivered and outfitted with District equipment. All buses have been ordered with expected delivery by January-February 2026.

Elementary Campus Refresh
October 2026
-
Bond 2025 seeks to enhance the library space at existing elementary campuses that were built prior to 2021, so that they are aligned more closely with the standards that have been established with the opening of Grand Oaks Elementary and West Elementary.
-
Enhancements will include new flooring, paint, graphics, furniture, and STEM lab equipment.
-
Serving as a pilot campus, the Canyon Pointe Elementary library was the first library refresh scheduled and completed during the Summer and Fall 2026.

September 2026
-
As part of the Campus Refresh projects, gym floor replacements at the following campuses were completed during Summer 2026:
- Tomball Elementary
- Tomball Intermediate
- Rosehill Elementary
- Willow Creek Elementary
- Decker Prairie Elementary
-
Campus Refresh projects will continue over the life of the Bond 2025 program, targeting older campuses to bring them into alignment with District standards.



August 2026
-
Elementary campus refresh projects are underway at Tomball Elementary, Decker Prairie Elementary, Willow Creek Elementary, Canyon Pointe Elementary, Rosehill Elementary as part of the 2025 Bond campus refresh projects.
-
Refresh projects may include updates to libraries, gymnasiums, front offices, and cafeterias, and will create bright, inviting spaces that support learning, collaboration, and daily campus life.
- Construction activities will continue throughout the early weeks of the school year, with work carefully coordinated to minimize disruptions to teaching and learning.
-
These campus refresh projects introduce consistent branding, colors, and design elements throughout Tomball ISD, creating a cohesive experience for students, staff, and visitors while celebrating the district's identity.




April 2026
- In March 2026, the Tomball ISD Board of Trustees approved the replacement of gym floors at the following campuses:
- Tomball Elementary
- Decker Prairie Elementary
- Willow Creek Elementary
- Rosehill Elementary
- Tomball Intermediate
- Replacement of the gym floors at these campuses will mirror the gym flooring found at West Elementary and West Intermediate, and will be completed during Summer 2026.

Student & Staff Device Refresh
September 2026
-
Phase 2 of the technology device refresh for staff is currently underway. All devices have been received, and deployment is either scheduled or in progress for the following campuses.
- Creekside Park
- Northpointe Intermediate
- Canyon Pointe Elementary
- Wildwood Elementary
- Willow Wood Junior High
- Oakcrest Intermediate
- Lakewood Elementary
- Willow Creek Elementary

June 2026
-
At the May 2026 Board meeting, the Board of Trustees approved Phase 2 of the technology device refresh for staff at the following campuses:
- Creekside Park
- Northpointe Intermediate School
- Canyon Pointe Elementary School
- Wildwood Elementary School
- Willow Wood Junior High
- Oakcrest Intermediate School
- Lakewood Elementary School
- Willow Creek Elementary School
November 2025
- In October 2025, the Tomball ISD Board of Trustees approved the purchase of student and staff technology devices.
-
This initial purchase of student devices will refresh/replace computers in use at the THS and TMHS computer labs.
-
Phase 1 of the staff laptop replacements will replace laptops for all professional staff at Decker Prairie Elementary, Tomball Elementary, Tomball Junior High, and Tomball Star Academy.
-
Safety & Security
September 2026
-
Phase 1 of installation of the district-wide radio communication system is complete. The system installation at the Tomball Event Center will provide reach to the West Complex, the Elmer & Beckendorf Educational Complex, and all bus transportation radios.
-
Phase 2 will include infrastructure upgrades for Tomball High School, Tomball Memorial High School, and Creekside Park.
-
The radio communication system project is intended to strengthen both daily communication and emergency response efforts.

June 2026
-
At the May 2026 Board meeting, the Board of Trustees approved the purchase of a district-wide radio communication system intended to strengthen both daily communication and emergency response efforts.
Facility Infrastructure
June 2026
- At the May 2026 Board meeting, the Board of Trustees approved the selection of Air Conditioning Innovative Solutions (ACIS) to complete the replacement of HVAC equipment at the Tomball ISD Staff Development Center.
- This project will include the replacement of existing chillers, water pumps, and infrastructure to ensure proper system performance and reliability.
May 2026
- No new infrastructure projects were approved by the Tomball ISD Board of Trustees in April, but a number of previously approved projects have been completed or are nearing completion including:
-
-
Tomball High School Fieldhouse HVAC - 99% Complete
-
Tomball Junior High HVAC - Completed
-
Tomball High School Chiller Rebuild - Completed
-
High Volume Low Speed Fan Replacements - Completed
-
Smoke Detector Replacements (3 Campuses) - Completed
-
PA System Replacements (4 Campuses) - Completed
-
-




April 2026
- In March 2026, the Tomball ISD Board of Trustees approved projects for the initial replacement of network switching equipment and network cabling at existing campuses to address devices that have reached end of life and increase campus connectivity.
March 2026
- In February 2026, the Tomball ISD Board of Trustees approved DBR Engineering Consultants to provide professional services for Chiller Repair & Replacement Package #1. This project will address aging HVAC equipment at the following facilities:
- Lakewood Elementary
- Decker Prairie Elementary
- Willow Creek Elementary
- Tomball High School - Building Controls
- Technology Building
- Central Office - Administration Building
December 2025
- In November 2025, the Tomball ISD Board of Trustees approved the purchase of fire panel replacements in order to upgrade existing fire alarm control systems for 8 facilities district-wide. This project will address the following facilities:
- Timber Creek Elementary
- Canyon Pointe Elementary
- Creekside Forest Elementary
- Tomball Elementary
- Willow Creek Elementary
- Ancillary Building
- Tomball High School Field House
- Tomball High School Aquatic Center
- In November 2025, Tomball ISD initiated the purchase and scheduling of smoke detector replacements at Tomball Intermediate, Creekside Park Junior High, and Wildwood Elementary. This project will replace devices that have reached end of life and will address additional campuses in future phases.
- In November 2025, Tomball ISD initiated the purchase and scheduling of PA intercom system upgrades at campuses where the PA systems have reached end of life and can no longer be updated. This project will address the following campuses:
- Tomball Elementary
- Northpointe Intermediate
- Tomball High School
- Willow Creek Elementary
November 2025
- HVAC equipment rebuild/replacement at THS Field House
- Concrete work for the new chiller and demo of two outside air units has been started.
- Hunton services is completing deck work needed to facilitate their work in the mechanical rooms.
- HVAC building automation system at the THS Field House
- Engineering of the new automation system has been completed by Automated Logic.
- Rebuild of Chillers at THS
- Hunton Services is scheduled to begin the rebuild of existing chillers at Tomball High School in November.

- HVAC equipment rebuild/replacement at TJHS
- Hunton Services is working nightly to complete this project and are roughly 50% complete.
- High Volume Low Speed fan replacements
- Replacement of the fans at THS, TMHS, and Tomball Innovation Center Warehouse has been completed at this time.

October 2025
-
In June 2025 the Tomball ISD Board of Trustees approved the purchase of three temporary instructional buildings already in service at Rosehill Elementary School. Taking ownership of the temporary buildings will reduce rental costs and ensure that TISD has sufficient instructional space for projected growth.
-
In August 2025, the Tomball ISD Board of Trustees approved Hunton Services to perform replacements and rebuilds for HVAC equipment at TJHS & the THS Field House. At this time work is being scheduled and coordinated to minimize impacts to daily operations.
-
In August 2025, the Tomball ISD Board of Trustees approved Automated Logic to update the HVAC building automation system at the THS Field House. Updates to the automation system will be completed alongside the replacement and rebuild of equipment.
-
In August 2025, the Tomball ISD Board of Trustees approved the purchase of high volume low speed fan replacements at the TMHS agricultural barn, THS agricultural barn and TIC warehouse. At this time the equipment order has been placed.

Athletics
June 2026
- At the June 2026 Board meeting, the Board of Trustees re-approved the purchase of replacement bleachers at Tomball High School after moving on from the previously awarded vendor.
- Due to the delays with the original vendor, product availability, and impact to campus activities, the bleacher replacement project will be completed during the Summer of 2027.
February 2026
- During the January 2026 Board meeting, the Board of Trustees approved the purchase and replacement of bleachers for the competition and auxiliary gyms at Tomball High School.
- The new bleachers are a step toward bringing Tomball High into alignment with the facilities at Tomball Memorial and Tomball West High School.
Bond 2021 Updates
- Tomball West High School
- Creekside Park 5th Grade Addition
- West Complex Site Development
- West Intermediate
- West Elementary
- Early Excellence Academy
- Tomball Star Academy
- TIC Building #4 - Maintenance
- Tomball Agricultural Center
- Tomball High School Renovations
- Buses
- TIC Building #6 - CTE
Tomball West High School
Tomball ISD's third comprehensive High School opened August 2026, serving grades 9 through 10 (will expand 9-12 by year 3) with a design capacity of 3,000 students at 531,762 sq. ft.
October 2026
-
The Tomball West High School agricultural project barn opened to students and animals in September 2026.
-
The project barn will provide students with a modern, on-campus facility to support agricultural science instruction, FFA participation, and livestock project development while offering hands-on experiences in animal care, agricultural leadership, and career preparation.
-
The facility will also provide safe, secure, and appropriately designed housing for student project animals.

September 2026
Agricultural Project Barn & Competitive Soccer Field
-
Both the Agricultural Project Barn and Soccer Field at Tomball West High School have reached substantial completion.
-
Work is currently being finalized on remaining punch list items.


August 2026
Grand Opening & Ribbon Cutting
-
Tomball ISD celebrated the official Grand Opening and Ribbon Cutting of its third comprehensive high school, Tomball West High School on July 27.
- Over 1,000 students, staff, families and community members celebrated the historic day.
Tomball ISD Officially Opens Tomball West High School


Agricultural Project Barn & Competitive Soccer Field
- As of July 29, final wrap up is underway for both facilities as the contractors work through punch list items prior to the start of school.


June 2026
- Construction of Tomball West High School continues to progress as planned and remains on schedule for the start of the 2026–2027 school year.
- An official ribbon-cutting ceremony is planned for July 27 at 9 AM, giving the community an opportunity to celebrate the opening of Tomball ISD’s newest high school before students arrive in August.

Agricultural Project Barn & Competitive Soccer Field
-
The Agricultural Project Barn is 85% complete with the canopy due to be installed next week and louvers the following week. The project is aggressively targeting completion by the end of this month.
- As of June 3, the TWHS Soccer Stadium is 90% complete with the scoreboard scheduled to be installed next week.


May 2026
- Construction of Tomball West High School continues to progress as planned.
- Artificial turf surfaces are now installed on the football, baseball, and softball fields. The track around the football field is now complete.
- Exterior is complete with interior near completion with the exception of the Auditorium.


Agricultural Project Barn & Competitive Soccer Field
-
As of April 15th, the pre-engineered metal building structure has been erected and was ready for roofing panels.
- The soccer field house exterior is nearing completion and sod for the field surface is being laid.


April 2026
- Construction of Tomball West High School continues to progress as planned with the Board of Trustees approving the purchase of student and staff technology devices during the March 2026 Board meeting.
- Artificial turf surfaces are currently being installed on the football, baseball, and softball fields.


Agricultural Project Barn & Competitive Soccer Field
-
Gamma Construction has completed the rough grading of the privacy berm separating the Project Barn and Soccer Field. As of March 26th, 75% of the pre-engineered metal building structure has been erected.

March 2026
- Construction of Tomball West High School continues to progress as planned with the Board of Trustees approving the purchase of classroom smart panels and band uniforms during the February 2026 Board meeting.

Agricultural Project Barn & Competitive Soccer Field
-
Gamma Construction continues to progress as planned with the building pad and parking completed for both facilities during February.

February 2026
- Construction of Tomball West High School continues to progress as planned.
-
The Board of Trustees approved the purchase of all culinary arts equipment so that Tomball West High School will open with a fully equipped kitchen for students.



Agricultural Project Barn & Competitive Soccer Field
-
Gamma Construction continues to progress as planned with the building pad completed and underground utilities at 80% complete.
-
The privacy bern separating the Ag Barn and Soccer Field has been rough graded at this time.

January 2026
- Construction of Tomball West High School is progressing as planned and remains on track for opening in August 2026.
-
Flooring is currently being installed throughout the building including the gymnasiums.



Agricultural Project Barn & Competitive Soccer Field
-
Gamma Construction continues to progress as planned with the building pad completed and underground utilities at 80% complete.

December 2025
-
Construction of Tomball West High School is progressing as planned and remains on track for opening in August 2026.
-
Flooring is currently being installed throughout the building including the gymnasiums.


Agricultural Project Barn & Competitive Soccer Field
-
Gamma Construction has continued the site work for the two facilities and has begun installation of the underground utilities. Grading for the berm that separates the two facilities is also in progress as part of the site work.

November 2025
- Construction of Tomball West High School remains ongoing, with the athletic fields reaching substantial completion in October. Final work to install wear surfaces such as turf and netting will be completed in Spring 2026.
- In October 2025, the Tomball ISD Board of Trustees approved the purchase of technology network infrastructure equipment for Tomball West High School.


Agricultural Project Barn & Competitive Soccer Field
-
Gamma Construction began site work for both facilities in October 2025 with site grading and underground utility infrastructure.

October 2025
-
Construction on Tomball West High School is ongoing at this time with the building being fully dried in allowing for interior work to be completed.
-
All athletic fields are approaching substantial completion, with artificial turf being installed in spring 2026.
-
Coordination for the procurement of final graphics packages, furniture, supplies and equipment will be ongoing this fall and spring 2026.


Agricultural Project Barn & Competitive Soccer Field
-
Gamma Construction was approved by the Tomball ISD Board of Trustees at the September 2025 Board Meeting to serve as the contractor for these Tomball West High School facilities.
-
Construction will begin in October 2025.

Creekside Park 5th Grade Addition
September 2026
-
Tomball ISD celebrated the official opening of Creekside Park’s 5th grade addition on August 11, 2026.
-
With this addition, Creekside Park becomes Tomball ISD’s only campus serving students in grades 5-8.


August 2026
- Construction on the 5th grade addition has reached substantial completion.
- Final cleanup of the building and parking lots are underway to prepare the campus for staff and students this August.


June 2026
- Construction on the 5th grade addition continues to progress as planned.
- All exterior brick and stone work has been completed, with interior finish work continuing.
- The cafeteria expansion will continue through the majority of the summer, with flooring replacement as a major component still to be completed.


May 2026
- Construction on the 5th grade addition continues to progress as planned.
- Contractors have made significant progress over the last month to get the cafeteria expansion dried in. Additionally all infrastructure equipment has gone through the startup and testing phase.

April 2026
- Construction on the 5th grade addition continues to progress as planned, with the Board of Trustees approving the purchase of student and staff technology devices including classroom interactive flat panels during the March 2026 Board meeting.

March 2026
- Construction on the 5th grade addition continues to progress as planned, with exterior masonry and stonework nearly complete.
- Contractors are preparing for the cafeteria expansion, installing temporary walls and protected walkways while work is being done outside the building.


February 2026
- Construction on the 5th grade addition continues to progress as planned, with interior masonry work at 98% complete and exterior stone work progressing without issue.
- Hydro mulch of the detention pond has been completed and temporary fencing is expected to be removed and replaced with permanent fencing in the next few weeks.

January 2026
-
Construction on the 5th grade addition continues to progress as planned, with interior masonry work at 90% complete and exterior stone work underway.
-
A number of critical projects, including prep work for the cafeteria expansion, were completed during the Christmas break to ensure final summer work is completed as planned.


December 2025
- Construction on the 5th grade addition is ongoing at this time with all walls up, waterproofed and the roofing at 90% complete. Interior masonry and window installation is in progress and moving forward as planned. All necessary detention ponds for the expansion have been dug, with finish grading to be completed in December.


November 2025
- Construction on the 5th grade addition is ongoing at this time with all structural steel in place.
- During the Fall Break in October, additional concrete work was completed to facilitate the next stages of expansion for the CPJH cafeteria, which will begin in December 2025.


October 2025
- Construction on the 5th grade addition is ongoing at this time with approximately 95% of the structural steel erected.
- While work continues on the additional instructional spaces, the contractor will also utilize breaks for school holidays to begin work on the cafeteria expansion. This bulk of this work is expected to start during the Christmas break, and continue during the spring semester.


West Complex Site Development
September 2026
Forced Main Sewer Connection
-
Final connections from the West Complex to Tomball ISD’s wastewater treatment plant were made in August, with the system fully operational prior to the start of the 2026-2027 school year.
August 2026
Forced Main Sewer Connection
-
Deanco has completed the underground boring connecting the West Complex to Tomball ISD’s wastewater treatment plant. Final connections and cleanup is underway to have the system fully operational this August.
June 2026
Traffic Light at Mueschke Road
-
The traffic light at the intersection of Mueschke Road and Destination Drive has been completed but is not yet active as construction on Tomball West High School continues.
- The traffic light will be activated prior to the start of the 2026-27 school year.
May 2026
Traffic Light at Mueschke Road
-
While Destination Drive will serve as the main entrance to Tomball West High School, the entrances will be used for construction traffic only until the campus is opened in August 2026.
-
Access for thru-traffic to West Elementary and West Intermediate will not be available.
April 2026
Forced Main Sewer Connection
-
Deanco was selected by the Tomball ISD Board of Trustees in March to complete the connection of the West Complex to the TISD Wastewater Treatment Plant. Work to clear the path for trench work began on March 26th.
March 2026
Forced Main Sewer Connection
-
Tomball ISD is in the planning stages to connect the West Complex sanitary sewer system to the District’s wastewater treatment plant.
Channel Extension
-
The extension will serve the West Complex, providing drainage and additional detention for the property. Construction of the channel over the last two months has been steady, with the channel path now connecting the West Complex to Little Cypress Creek.
- Select fill dirt from the channel construction is being spread across the undeveloped TISD property between West Elementary and Juergen Rd.

February 2026
Forced Main Sewer Connection
-
Tomball ISD is in the planning stages to connect the West Complex sanitary sewer system to the District’s wastewater treatment plant.
Channel Extension
-
The extension will serve the West Complex, providing drainage and additional detention for the property.
- Work began in December 2025 and is progressing with the construction of a headwall to provide structural support to direct water flow from the West Complex to the new channel for Harris County Flood Control.

December 2025
Channel Extension
-
In November 2025, the Tomball ISD Board of Trustees approved Deanco, Inc as the general contractor for completion of the Harris County Flood Control channel extension. The extension will serve the West Complex, providing drainage and additional detention for the property. Work is scheduled to begin in December and estimated to be completed prior to the opening of Tomball West High School in August 2026.

November 2025
Traffic Light at Mueschke Road
-
The concrete paving and curbs for the intersection at Mueschke Road and Destination Drive have been completed and are awaiting approval by Harris County.
-
While Destination Drive will serve as the main entrance to Tomball West High School, the entrances will be used for construction traffic only until the campus is opened in August 2026. Access for thru-traffic to West Elementary and West Intermediate will not be available.

October 2025
Traffic Light at Mueschke Road
-
The main entrance to Tomball West High School will be located off of Mueschke Road. At this time construction is in progress to add a turning lane and traffic light for the use of Tomball West High School.

West Intermediate
West Elementary
Early Excellence Academy
Tomball Star Academy
TIC Building #4 - Maintenance
February 2026
- Renovations to the existing office space at Tomball Innovation Center Warehouse facility is in its final stages and awaiting inspection and approval by the City of Tomball.

January 2026
- Renovations to the existing office space at Tomball Innovation Center Warehouse facility are complete and awaiting inspections at this time. This project consolidates the maintenance and warehouse operations within one facility.


December 2025
- Renovations to the existing office space at Tomball Innovation Center Warehouse facility is ongoing at this time. Completion of this project will consolidate our maintenance and warehouse operations within one facility.

November 2025
- Renovations to the existing office space at Tomball Innovation Center Warehouse facility is ongoing at this time.
- Completion of this project will consolidate our maintenance and warehouse operations within one facility.


October 2025
- Renovations to the existing office space at Tomball Innovation Center Warehouse facility is ongoing at this time.
- Completion of this project will consolidate our maintenance and warehouse operations within one facility.